Monday 7 July 2014

Day 26 - The home straight...

The fire doors arrived this morning. There's now 8 oak veneer panelled doors leaning up in our hallway now - 3 are fitted already. There's a standard door left to get, which makes the full set of 12.




The pipework has been added to link the radiators and shower room on the new floor into the main part of the system. The pipes will be boxed in over the course of the next few days.

The electrician has fitted the lights - recessed downlighters - in all 3 new rooms. The switches and sockets are all fitted on the new floor as well.



The end gable is complete, and the fascia fitted. Just the fascia, soffits and guttering to fit to the dormer, and the outside's about done. I've even put the first coat of black gloss on the front guttering and fascia we've retained - one more coat needed on the front, and then 2 coats on the back.


The tiling in the bathroom has also started, and should be finished tomorrow. Then the rest of the shower room can be fitted and we can start to get the decorating done.
The builders think they should be pretty much done by the end of this week. Then we get to start our hard work decorating and getting moved upstairs so we can decorate and move the girls into their new bedrooms, and then decorate the rest of the house...